Progress Management System
| Jenis | Total | Cutting | Bending | Welding | Grinding | Coating | Assy | Finish_goods | Delivry | Progress (%) |
|---|---|---|---|---|---|---|---|---|---|---|
| PROGRAM 1 | 2000 | 150 | 150 | 150 | 150 | 150 | 150 | 150 | 150 | 8% |
| PROGRAM 2 | 2000 | 150 | 150 | 150 | 150 | 150 | 150 | 150 | 150 | 8% |
| PROGRAM 3 | 2000 | 150 | 150 | 150 | 150 | 150 | 150 | 150 | 150 | 8% |
| PROGRAM 4 | 2000 | 150 | 150 | 150 | 150 | 150 | 150 | 150 | 150 | 8% |
| PROGRAM 5 | 2000 | 150 | 150 | 150 | 150 | 150 | 150 | 150 | 150 | 8% |
| PROGRAM 6 | 2000 | 150 | 150 | 150 | 150 | 150 | 150 | 150 | 150 | 8% |
| Total Progress Project: 8% | ||||||||||
| Jenis | Total | Cutting | Bending | Welding | Grinding | Coating | Finish_goods | Delivry | Progress (%) |
|---|---|---|---|---|---|---|---|---|---|
| PROGRAM 1 | 1000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0% |
| PROGRAM 2 | 1000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0% |
| PROGRAM 3 | 1000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0% |
| PROGRAM 4 | 1000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0% |
| PROGRAM 5 | 1000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0% |
| PROGRAM 6 | 1000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0% |
| Total Progress Project: 0% | |||||||||
| Jenis | Total | Cutting | Grinding | Rtg | Galvanis | Finish_galva | Finish_goods | Delivry | Progress (%) |
|---|---|---|---|---|---|---|---|---|---|
| Plat Mounting | 180 | 180 | 180 | 180 | 180 | 180 | 180 | 0 | 86% |
| Total Progress Project: 86% | |||||||||
| Jenis | Total | Cutting | Welding | Grinding | Painting | Finish_goods | Delivry | Progress (%) |
|---|---|---|---|---|---|---|---|---|
| 1. SITE HANTARIRING ESTATE | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 83% |
| Assy Tiang | 39 | 39 | 39 | 39 | 39 | 39 | 0 | 83% |
| Assy Pintu | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 83% |
| 2. SITE TEPIAN BARU | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 83% |
| TIANG 1 | 40 | 40 | 40 | 40 | 40 | 40 | 0 | 83% |
| TIANG PINTU | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 83% |
| PINTU PAGAR | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 83% |
| 3. SITE PAGERUNGAN KECIL | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 83% |
| Assy Tiang | 46 | 46 | 46 | 46 | 46 | 46 | 0 | 83% |
| Assy Pintu | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 83% |
| 4. SITE DESA AWAYAN | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 83% |
| Assy Tiang | 68 | 68 | 68 | 68 | 68 | 68 | 0 | 83% |
| Assy Pintu | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 83% |
| 5. SITE PT LOGING | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 83% |
| Tiang 1 | 18 | 18 | 18 | 18 | 18 | 18 | 0 | 83% |
| Tiang Pintu | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 83% |
| Pintu | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 83% |
| 6. SITE PAPANDANGAN | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 83% |
| Assy Tiang | 61 | 61 | 61 | 61 | 61 | 61 | 0 | 83% |
| Assy Pintu | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 83% |
| 7. SITE MALASOKA | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 83% |
| Tiang 1 | 67 | 67 | 67 | 67 | 67 | 67 | 0 | 83% |
| Tiang Pintu | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 83% |
| Pintu | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 83% |
| Total Progress Project: 83% | ||||||||
| Jenis | Total | Cutting | Bending | Welding | Grinding | Setting | Painting | Finish_goods | Delivry | Progress (%) |
|---|---|---|---|---|---|---|---|---|---|---|
| PAGAR | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 0 | 63% |
| Total Progress Project: 63% | ||||||||||
| Jenis | Total | Cutting | Bending | Coating | Assy | Finish_goods | Delivry | Progress (%) |
|---|---|---|---|---|---|---|---|---|
| PROGRAM 1 | 23 | 23 | 23 | 23 | 23 | 23 | 0 | 83% |
| PROGRAM 2 | 23 | 23 | 23 | 23 | 23 | 23 | 0 | 83% |
| PROGRAM 3 | 23 | 23 | 23 | 23 | 23 | 23 | 0 | 83% |
| PROGRAM 4 | 23 | 23 | 23 | 23 | 23 | 23 | 0 | 83% |
| PROGRAM 5 | 23 | 23 | 23 | 23 | 23 | 23 | 0 | 83% |
| PROGRAM 6 | 23 | 23 | 23 | 23 | 23 | 23 | 0 | 83% |
| Total Progress Project: 83% | ||||||||
| Jenis | Total | Cutting | Bending | Welding | Grinding | Coating | Assy | Finish_goods | Delivry | Progress (%) |
|---|---|---|---|---|---|---|---|---|---|---|
| PROGRAM 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 75% |
| Total Progress Project: 75% | ||||||||||
| Jenis | Total | Cutting | Bending | Welding | Grinding | Coating | Assy | Finish_goods | Delivry | Progress (%) |
|---|---|---|---|---|---|---|---|---|---|---|
| PANEL GW | 4 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 19% |
| Total Progress Project: 19% | ||||||||||